ICPM - Inventory Planning Data Maintenance

New features added, version 7.5.2, 7.5.3, 8.1, 7.5.4, 8.4, 7.5.4 Patches, 8.4 Patches

See Also Programs

Program ICPM, Inventory Planning Data Maintenance, is used to maintain material requirements planning (MRP) and master production scheduling (MPS) data for inventory items for both the logged in enterprise and logged in plant.

See Also

Determining Item Planning Parameters

Creating Plant Records & Copying Manufacturing Enterprise Defaults

Entering Enterprise Item Planning Information

Entering Plant Item Planning Information

ICPM Action Buttons

 

Determining Item Planning Parameters

Planning parameters can be set up at the plant level on the Plant Tab in this program and those parameters override the parameters set up on the Default ME Tab in this program.. Most of this data is used by other parts of the system: material planning, master scheduling, reorder point calculations, work order release, and purchasing.

If any record exists on the Plant Tab for an item, the system will take all information from that tab over the information on the Default ME Tab. This includes fields that have been left blank on the Plant Tab.

Preferred Vendor

The preferred vendor that is used in the purchasing module is set up in this program. The preferred vendor for an item is determined as follows:

Reorder Point

In order for the reorder point feature to operate, the order code must be set to R and a reorder point quantity must be entered in the reorder point field.

Inventory Comments

Inventory comments can be entered and maintained with this program. Comments entered for the item in program ICMM, Inventory Master Maintenance, program ICSM, Inventory Sales Data Maintenance, ICPM, Inventory Planning Data Maintenance, and ICCM, Inventory Cost Data Maintenance, will be displayed and can be maintained in this program.

Proxy Item Planning

When setting up planning information for proxy items for the Material Proxy Planning (PXM) Module, be sure to set the lead time information to match that of the set of items that the proxy item represents.

 

Creating Plant Records & Copying Manufacturing Enterprise Defaults

When you press the [Create Plant Record] button to create a plant planning record or the [Copy ME Defaults] button to replace the current values for the item, the defaults from program ICPD, Inventory Planning Data Defaults, are selected the in the following order of precedence. The X's and Y's indicates that the entries in the fields in program ICPD, Inventory Planning Data Defaults match the user's logged in manufacturing enterprise and plant. The A's and B's indicate that the entries in the field's match the manufacturing enterprise and plant code that are displayed at the top of this program in the Mfg Ent and Show Plant fields.

 

Def Unit Code

Def Plant Code

ME Code

Plant Code

Explanation

X

Y

A

B

When the item planning record is created in this program, the defaults will come first from the ICPD record that has entries in the default unit code, default plant code, ME code, and plant code fields where the user's logged in manufacturing enterprise and plant match the default unit code and default plant code, and the ICPM manufacturing enterprise and show plant match the ME code and plant code.

X

blank

A

B

If the previous record does not exist, the defaults will come from the ICPD record that has entries in the default unit code, ME code, and plant code fields, where the default unit code matches the user's logged in manufacturing enterprise and the ICPM manufacturing enterprise and show plant match the ME code and plant code.

blank

blank

A

B

If the previous record does not exist, the defaults will come from the ICPD record that has no entries in the default unit code and default plant code fields, and has entries in the ME code and plant code fields, where the entries in the ME code and plant code fields match the ICPM manufacturing enterprise and show plant.

X

Y

A

blank

If the previous record does not exist, the defaults will come from the ICPD record that has entries in the default unit code, default plant code, and ME code fields where the default manufacturing enterprise and default plant code match the user's logged in manufacturing enterprise and plant, and the ME code matches the ICPM manufacturing enterprise.

X

Y

blank

blank

If the previous record does not exist, the defaults will come from the ICPD record that has entries in the default unit code and default plant code fields, but no entries in the ME code and plant code fields. The default unit code and default plant code must match the user's logged in manufacturing enterprise and plant code.

X

blank

A

blank

If the previous record does not exist, the defaults will come from the ICPD record that has entries in the default unit code and ME code fields and no entries in the default plant code and plant code fields. The default unit code field must match the user's logged in manufacturing enterprise and the ME code must match the ICPM manufacturing enterprise.

X

blank

blank

blank

If the previous record does not exist, the defaults will come from the ICPD record that has an entry in the default unit code field and no entries in the default plant code, ME code, or plant code fields. The default unit code must match the user's logged in manufacturing enterprise.

blank

blank

A

blank

If the previous record does not exist, the defaults will come from the ICPD record that has an entry in the ME code field and no entries in the default unit code, default plant code, or plant code fields. The ME code must match the ICPM manufacturing enterprise.

blank

blank

blank

blank

If the previous record does not exist, the defaults will come from the ICPD record that has no entries in the default unit code, default plant code, ME code, or plant code fields.

 

Entering Enterprise Item Planning Information

You can only modify enterprise item planning information if the ICPM_MODE parameter is set to A for your user in program MURM, Initialization Parameter Maintenance, and you selected [Plants and Mfg Enterprise] when you ran the program.

1. In the Show Plant pop-list, select the desired plant for the logged in manufacturing enterprise.

2. In the Item No field, query the item for which you are entering planning information.

3. Click on the Default ME Tab. The background of the tab is dark gray to distinguish it from the plant tab.

Operations

1. In the Operations section, in the Planner Code field, enter the planner code for this item, if desired.

2. In the Buyer Code field, enter the buyer code for this item, if desired.

3. Set the Make or Buy pop-list to the desired setting. Choices are Manufactured or Purchased.

6. Set the Manufacturing Method pop-list to the desired setting. Choices are Work Order or Production Schedule.

7. In the Preferred Vendor field, enter the vendor number that is the preferred vendor for this item.

8. In the Order Policy field, enter the desired order policy for this item. The order policy determines the type of orders created by material requirements planning (MRP) and master production scheduling (MPS).

9. In the Order Code field, enter the order code. The order code indicates to the system whether the item is manually or automatically planned and the type of planning to be done. It is also used to cover the generation of stock transfer orders.

10. In the Safety Factor field, enter the safety factor, if appropriate. The safety factor is used in program FCCP, Forecast Calculation, to calculate the safety stock quantity in statistical forecasts.

11. Set the Operation Scheduling pop-list to the desired setting. This will determine the type of scheduling, either forward or backward, that is to be used for this item in work order and production schedule releases. The default setting comes from program SPMM, System Parameters/Default Maintenance.

12. Press [Commit].

Lot Sizing

1. In the Min Prod Rate field, enter the minimum production rate, if appropriate. This is the minimum production rate for the item, used for rate based items in master scheduling.

2. In the Max Prod Rate field, enter the maximum production rate, if appropriate. This is the maximum production rate for the item, used for rate based items in master scheduling.

3. In the Prod Period field, enter the production period for the minimum and maximum rates. If you have entered either the minimum or maximum production rate and leave this field blank, the program supplies "1" as the default when you commit the record.

4. In the Safety Stock Qty field, enter the minimum on hand balance that is carried by inventory to compensate for uncertainty in forecast and lead time.

5. In the Shrinkage % field, enter the shrinkage percent, if appropriate.

6. In the Max Stock Qty field, enter the maximum stock quantity, if appropriate.

7. In the Target Stock Qty field, enter the quantity that should remain in the 'To Location' after the moves are completed and the allocations are filled. This quantity is added to the move quantity in program ICRC, Inventory Replenishment, when inventory replenishment moves are calculated.

This field is also updated in program ICEM, Item Plant Maintenance.

8. In the Reorder Point field, enter the reorder point quantity, if appropriate.

9. In the Min Order Qty field, enter the minimum order quantity, if appropriate.

10. In the Order Multiple field, if appropriate enter the increment used by material requirements planning (MRP) and master production scheduling (MPS) in creating orders. This is used in conjunction with the order policy.

11. In the Weeks Supply field, enter the week supply, if appropriate.

12. In the EOQ field, enter the quantity for the standard EOQ calculation for lot sizing. However, this is only for reference purposes and not used by the system.

13. In the Mgmt Reserve field, if appropriate enter the extra quantity that is held aside in addition to the safety stock. It is treated by the system as an extra stock buffer and is used by material requirements planning (MRP) and master production scheduling (MPS). For serial control items, this must be an integer.

14. Press [Commit].

Case Qty

1. Set the SR Default Qty Rule pop-list to the desired setting. Choices are Order Quantity and Case Quantity.

2. In the Case Qty field, enter the case quantity, if appropriate. If the SR Default Qty field is set to Case Quantity, this is the number of units equal to one case.

3. In the Per Pallet field, enter the number of cases per pallet for the item, if appropriate.

4. In the Container Type field, enter the default container type, if appropriate.

5. Press [Commit].

Forecast

1. Set the Statistical Option pop-list to the desired setting. The choices are Yes, No, and Track.

2. In the Group field, enter the forecast group from program FCGM, Forecast Group Maintenance, to which the item belongs, if appropriate.

3. Set the Alpha pop-list to the desired setting, if appropriate. The choices are low, medium, and high.

4. Set the Base Option pop-list to the desired setting, if appropriate. Choices are Orders and Shipments.

5. Press [Commit].

Lead Time

1. In the Lead Time 1, Lead Time 2, and Lead Time 3 fields, enter the lead times for the item, if appropriate. There are three fields for lead times in case you wish to categorize the lead times. The sum of the three are displayed in the Total Lead Time field.

2. In the Fixed LT field , the fixed lead time is the number of days to set up the item. It is calculated by the system from the routing, but it is not used by material requirements planning (MRP) or master production scheduling (MPS). You cannot maintain this field.

3. In the Variable LT field, the variable lead time is the runtime in days, calculated by the system. It is not used by material requirements planning (MRP) or master production scheduling (MPS). You cannot maintain this field.

4. In the Accum LT field, the accumulated lead time is the longest lead time path when exploding down the bill of material for the item. You cannot maintain this field.

5 In the Item LT Group field, enter the lead time group for this item, if appropriate. Lead time groups are set up in program ICLT, Item Lead Time Group Maintenance, and the lead time assigned to the group overrides the individual settings for items to which the lead time group is assigned.

6. Press [Commit].

MPS

1. In the MPS Planner field, enter the MPS planner code for this item, if desired.

2. In the Round Method pop-list, select the forecast rounding method for this item, if appropriate. The forecast rounding method operates with the forecast round to quantity to determine the rounded daily forecast actually used in master production scheduling (MPS) calculations.

3. In the Round Qty field, enter the forecast round to quantity, if appropriate.

4. Set the MPS ATP Method pop-list for master scheduling to the desired setting. The choices are Cumulative and Periodic.

5. In the MPS Trap % field, enter the master production schedule trap percentage for this item, if appropriate. The trap percentage is used to highlight individual customer demands that are greater than this percentage of the master production schedule (MPS) within a period.

6. Set the MPS ACC LT Override flag to the desired setting.

7. Press [Commit].

WOs

1. Set the WO Costs are Elemental flag to the desired setting.

2. Set the Cascade WO Release in OE flag to the desired setting.

3. Press [Commit].

User Defined

1. The User Ref 1 and User Ref 2 fields are for user-defined custom purposes. Enter the appropriate value.

2. Press [Commit].

 

Entering Plant Item Planning Information

1. In the Show Plant pop-list, select the desired plant for the logged in manufacturing enterprise.

2. In the Item No field, query the item for which you are entering planning information.

3. Click on the Plant Tab to view the plant planning information. If no plant planning record exists, the tab will be grayed out and you can press the [Create Plant Record] button to create the record for the logged in plant.

4. To copy the defaults for the item from the enterprise record on the Default ME Tab, press the [Copy ME Defaults] button.

Operations

1. In the Operations section, in the Planner Code field, enter the planner code for this item, if desired.

2. In the Buyer Code field, enter the buyer code for this item, if desired.

3. Set the Make or Buy pop-list to the desired setting. Choices are Manufactured or Purchased.

6. Set the Manufacturing Method pop-list to the desired setting. Choices are Work Order or Production Schedule.

7. In the Preferred Vendor field, enter the vendor number that is the preferred vendor for this item.

8. In the Order Policy field, enter the desired order policy for this item. The order policy determines the type of orders created by material requirements planning (MRP) and master production scheduling (MPS).

9. In the Order Code field, enter the order code. The order code indicates to the system whether the item is manually or automatically planned and the type of planning to be done. It is also used to cover the generation of stock transfer orders.

10. In the Safety Factor field, enter the safety factor, if appropriate. The safety factor is used in program FCCP, Forecast Calculation, to calculate the safety stock quantity in statistical forecasts.

11. Set the Operation Scheduling pop-list to the desired setting. This will determine the type of scheduling, either forward or backward, that is to be used for this item in work order and production schedule releases. The default setting comes from program SPMM, System Parameters/Default Maintenance.

12. Press [Commit].

Lot Sizing

1. In the Min Prod Rate field, enter the minimum production rate, if appropriate. This is the minimum production rate for the item, used for rate based items in master scheduling.

2. In the Max Prod Rate field, enter the maximum production rate, if appropriate. This is the maximum production rate for the item, used for rate based items in master scheduling.

3. In the Prod Period field, enter the production period for the minimum and maximum rates. If you have entered either the minimum or maximum production rate and leave this field blank, the program supplies "1" as the default when you commit the record.

4. In the Safety Stock Qty field, enter the minimum on hand balance that is carried by inventory to compensate for uncertainty in forecast and lead time.

5. In the Shrinkage % field, enter the shrinkage percent, if appropriate.

6. In the Max Stock Qty field, enter the maximum stock quantity, if appropriate.

7. In the Target Stock Qty field, enter the target stock quantity for the item.

8. In the Reorder Point field, enter the reorder point quantity, if appropriate.

9. In the Min Order Qty field, enter the minimum order quantity, if appropriate.

10. In the Order Multiple field, if appropriate enter the increment used by material requirements planning (MRP) and master production scheduling (MPS) in creating orders. This is used in conjunction with the order policy.

11. In the Weeks Supply field, enter the week supply, if appropriate.

12. In the EOQ field, enter the quantity for the standard EOQ calculation for lot sizing. However, this is only for reference purposes and not used by the system.

13. In the Qty In Reserve field, if appropriate enter the extra quantity that is held aside in addition to the safety stock. It is treated by the system as a type of safety stock and is used by material requirements planning (MRP) and master production scheduling (MPS). For serial control items, this must be an integer.

14. Press [Commit].

Case Qty

1. Set the SR Default Qty Rule pop-list to the desired setting. Choices are Order Quantity and Case Quantity.

2. In the Case Qty field, enter the case quantity, if appropriate. If the SR Default Qty field is set to Case Quantity, this is the number of units equal to one case.

3. In the Per Pallet field, enter the number of cases per pallet for the item, if appropriate.

4. In the Container Type field, enter the default container type, if appropriate.

5. Press [Commit].

Forecast

1. Set the Statistical Option pop-list to the desired setting. The choices are Yes, No, and Track.

2. In the Group field, enter the forecast group from program FCGM, Forecast Group Maintenance, to which the item belongs, if appropriate.

3. Set the Alpha pop-list to the desired setting, if appropriate. The choices are low, medium, and high.

4. Set the Base Option pop-list to the desired setting, if appropriate. Choices are Orders and Shipments.

5. Press [Commit].

Lead Time

1. In the Lead Time 1, Lead Time 2, and Lead Time 3 fields, enter the lead times for the item, if appropriate. There are three fields for lead times in case you wish to categorize the lead times. The sum of the three are displayed in the Total Lead Time field.

2. In the Fixed LT field , the fixed lead time is the number of days to set up the item. It is calculated by the system from the routing, but it is not used by material requirements planning (MRP) or master production scheduling (MPS). You cannot maintain this field.

3. In the Variable LT field, the variable lead time is the runtime in days, calculated by the system. It is not used by material requirements planning (MRP) or master production scheduling (MPS). You cannot maintain this field.

4. In the Accum LT field, the accumulated lead time is the longest lead time path when exploding down the bill of material for the item. You cannot maintain this field.

5 In the Item LT Group field, enter the lead time group for this item, if appropriate. Lead time groups are set up in program ICLT, Item Lead Time Group Maintenance, and the lead time assigned to the group overrides the individual settings for items to which the lead time group is assigned.

6. Press [Commit].

MPS

1. In the MPS Planner field, enter the MPS planner code for this item, if desired.

2. In the Round Method pop-list, select the forecast rounding method for this item, if appropriate. The forecast rounding method operates with the forecast round to quantity to determine the rounded daily forecast actually used in master production scheduling (MPS) calculations.

3. In the Round Qty field, enter the forecast round to quantity, if appropriate.

4. Set the MPS ATP Method pop-list for master scheduling to the desired setting. The choices are Cumulative and Periodic.

5. In the MPS Trap % field, enter the master production schedule trap percentage for this item, if appropriate. The trap percentage is used to highlight individual customer demands that are greater than this percentage of the master production schedule (MPS) within a period.

6. Set the MPS ACC LT Override flag to the desired setting.

7. Press [Commit].

WOs

1. Set the WO Costs are Elemental flag to the desired setting.

2. Set the Cascade WO Release in OE flag to the desired setting.

3. Press [Commit].

User Defined

1. The User Ref 1 and User Ref 2 fields are for user-defined custom purposes. Enter the appropriate value.

2. Press [Commit].

 

ICPM Action Buttons

Create Plant Record

Press this button to create the plant planning record for an item when a plant item planning record does not exist for the item

Copy ME Defaults

Press this button to copy the defaults from the enterprise planning record for the item on the Default ME Tab.

List of Plants image\ebx_946350415.gif

Press this button to display the list of plants that have an item planning record for the current item.